The Port of Salaverry project presented technical, logistical, and operational challenges from the outset. The region’s seismic activity required structural analysis using the finite element method, while the distance between Brazil and Peru called for international logistics, with fabrication sized to fit container shipping. The COVID-19 pandemic further complicated this scenario, bringing border closures and unpredictable freight lead times. The project also demanded robust anti-corrosion protection, given the aggressive environmental conditions of the region, and rigorous quality and shipping control, essential for a remote site with limited infrastructure. Even so, fabrication, delivery, and erection were completed on schedule, meeting the project’s quality, safety, and performance requirements.